Stafford Road will be closed between Johnson Road and Rosemont Road through Sept. 30.
The County is continuing the second phase of construction which requires closing the intersection of Childs Road and Stafford Road, and Stafford Road between Johnson Road and Rosemont Road. Stafford Road is scheduled to open to traffic on October 1.
Current construction activity: construction work is progressing on schedule. Crews are realigning the Childs Road intersection and constructing the new Pecan Creek culvert, retaining walls, and embankment for the new roundabout.

Estimated full schedule of closures:
- May 5 – July 14, 2025: Stafford Road and Johnson Road closed to thru traffic from north of Pattulo Way to south of Childs Road
- July 15 – Sept. 30, 2025: Stafford Road and Childs Road closed to thru traffic from north of Johnson Rd to south of Rosemont Road
- Oct. 1, 2025 – April 31, 2026: Childs Road closed to thru traffic. Stafford Road and Johnson Rd open to traffic.
- May 1 – Aug 31, 2026: Stafford Road and Childs Road closed to thru traffic from north of Johnson Road to south of Rosemont Road
- Sept. 1 – Sept 30, 2026: Stafford Road and Johnson Road closed to thru traffic from north of Pattulo Way to south of Childs Road
- Oct 1 – Dec 31, 2026: All roads open to traffic. Construction under flagging.
Stay up to date: Visit the project website for construction schedule updates at www.clackamas.us/engineering/st-rd-improvements.
Questions or comments? Contact project manager Jonathan Hangartner, PE at
503-742-4649 or jhangartner@clackamas.us.