Since the successful passing of the bond to fund the new South Shore Fire Station, the design phase has been moving forward full speed. Two main efforts are underway – Land Use applications and Schematic Design & Pricing.
The Land Use applications were reviewed in a “pre-application” meeting on August 20th. Key issues: two separate LU approvals are sought – one for the temporary fire station to be erected on the city-owned lot east of the existing fire station (where the reservoir and tennis court sit), and the second for the permanent new fire station. A few variances will be required to enable the fire engines to drive straight into the site, turn around behind the station, and enter through the back of the apparatus bay. This will eliminate the current safety problem of rigs backing in off South Shore Blvd.

Architects Hennebery Eddy are nearly complete with the Schematic Design phase. The design is similar to the early rendering shown during the bond campaign – single story apparatus bay (4 bays) and 2 story fire house with dorm rooms and all the other functions of a fire station. Several energy saving and environmental features are planned – PV cells on the roof, storm water retention gardens, run-off water oil separators and treatment equipment, and decontamination areas with negative air pressure (prevents carcinogens from entering the living quarters). The building is designed as an “essential structure” meaning it can survive and function after a major earthquake.
The builder, Bremik Construction, is now pricing the Schematic Design plans along with several alternates. These alternates will give the project team the necessary options to ensure the project stays on budget. Bremik plans to start construction on the temporary fire station in March or April, 2027. Once complete (around June), the fire crews will move into the temporary station and demolition/new construction on the permanent station will commence. Construction completion is planned for late summer in 2028.
See the slides of the current design presented at the Neighborhood Meeting of Sept. 3rd below: