As you’ve likely seen on message boards along Stafford Road, the first season of construction to improve safety officially begins Monday, May 5. Stafford Road will be closed to thru traffic between Johnson Road and Childs Road from May 5 through September 30, 2025. This includes the intersection at Stafford and Johnson Roads.

Estimated full schedule of closures:
- May 5 – July 14, 2025: Stafford Road and Johnson Road closed to thru traffic from north of Pattulo Way to south of Childs Road
- July 15 – Sept. 30, 2025: Stafford Road and Childs Road closed to thru traffic from north of Johnson Rd to south of Rosemont Road
- Oct. 1, 2025 – April 31, 2026: Childs Road closed to thru traffic. Stafford Road and Johnson Rd open to traffic.
- May 1 – Aug.31, 2026: Stafford Road and Childs Road closed to thru traffic from north of Johnson Road to south of Rosemont Road
- Sept. 1 – Sept. 30, 2026: Stafford Road and Johnson Road closed to thru traffic from north of Pattulo Way to south of Childs Road
- Oct. 1 – Dec. 31, 2026: All roads open to traffic. Construction under flagging.
There will be one signed detour route for truck and passenger vehicles along I-205, I-5, Boones Ferry Road, County Club Road. There may be other unsigned detour routes available depending on time of day and your destination. Please use caution near the work zone.
Stay up to date: Visit the project website for construction schedule updates at www.clackamas.us/engineering/st-rd-improvements.
Questions or comments? Contact project manager Jonathan Hangartner at
503-742-4649 or jhangartner@clackamas.us.