The key takeaway is simple: Stafford Rd from Rosemont Road to I-205 will remain closed until October 1. Even after the road reopens, construction crews will continue working under flagging operations, so delays and slow traffic should be expected.
Please plan alternate routes through September and allow extra travel time after October 1.
FYI – Updated Stafford Road Overall Completion Status
- Through August 31: Current Stafford Road/Childs Road closure remains in effect.
- September 1 – September 30: Stafford Road (partial closure) and Johnson Road closed to through traffic between Pattulo Way and Childs Road.
- October 1 – December 31: All roads open, with remaining construction completed under flagging operations.
For more information regarding the Stafford Road (Pattulo Way to Rosemont Road) Improvements visit Clackamas County project webpage here.